Carmel announces tentative construction schedule for 2019

Posted
and last updated

CARMEL — Though it’s only winter, it’s time to plan ahead for spring, summer, and fall — which, here in Indiana combine to be construction season.

Per a release on Carmel Link 2.0’s Facebook page, here is a tentative plan that the City of Carmel has for this year’s construction period.

Do note that the start and end dates have not been officially chosen, this is just a tentative schedule so you can keep these projects on your radar for when the weather does start to get nice.

City of Carmel’s Tentative 2019 Construction Schedule

Spring Schedule:

Monon Boulevard Construction :Will continue through the end of 2019

North Range Line Road Reconstruction: Asphalt and curb work mostly on the southbound lanes

Path Projects in South West Clay

  1. West 96th Street final surfacing

Cherry Creek Boulevard Expansion: Construction to complete the final phase to connect Hazel Dell Parkway to River Rd. This is expected to start in February and continue for 150 days.

Lowes Way Connector: Phase 2 continues to North Range Line Rd. This is a county-lead project that began in 2018.

Summer Schedule:

96th Street Corridor Projects:

  1. Gray Road & 96th Stree Roundabout: This should begin on or after June 1st and will be a partial closure, expected to continue for 75 days.
  2. Delegates Row & 96th Street Roundabout: This should begin on or after June 1st and will be a partial closure, expected to continue for 75 days.
  3. Keystone Interchange: Construction is expected to continue through 2019 on this project.

Guilford Road Reconstruction is expected to last 150 with various facets:

  1. Road Work: Main Street to City Center on or after June 1st
  2. Culvert Replacement: Adjacent to Carmel Middle School
  3. Roundabout at Main Street: Start on or after August 1st

126th Street Path Project: This project will start on or after June 1st and is expected to continue for 180 days. Crews will be adding a new multi-use path to the City right-of-way connecting Keystone Parkway and Hazel Dell Parkway along the north side of the road. This is a federal aid project. There won’t be any eminent closure of the road, but there will be flagging (as needed) throughout the project.

Duke Transmission Line: This project is expected to continue for 180 days. The Duke Transmission Line continues to be buried through the center of town. This phase will continue through Midtown and crossing Main Street. Expect rolling closure one block at a time.

116th Street & Range Line Road Roundabout: This will begin on or after August 1st and is expected to continue for 120 days.

  1. Roundabout at 116th Street: Partial Closure
  2. Roundabout at Medical Drive: Partial Closure
  3. Culvert on Range Line, south of 116th Street: Full Closure
  4. Road work from Carmel Drive to 116th Street: Partial Closure

Carmel Drive & Pennsylvania Street Roundabout: Standard 2-lane roundabout that is expected to continue for 75 days.

Veteran’s Way (Fire House Townhomes Project)

  1. Ditch work along Monon Trail
  2. Two culverts and a bridge
  3. Road reconstruct (between Veteran’s Garage and Fire Station)

136th Street Path: Multi-use path from Range Line Road to Stadium Drive—this is expected to continue for 100 days

Main Street Path Work: East of Keystone Parkway

Fall Schedule:

Range Line Road Reconstruction continued (City Center to Elm Street): This is expected to continue for 100 days.

  1. Roundabout at 6th Street: Full closure
  2. Street reconstruction: Partial closure

North Gray Road Path: This work is expected to continue for 75 days

MORE TOP STORIES| Driver critical after going airborne off I-65 and into a building | Indiana woman killed in North Carolina lion attack | Indiana woman killed in North Carolina lion attack | Car dealer agrees to pay $62K to customers after Attorney General files lawsuit | Tyler Trent loses his battle with bone cancer